Case studies · Jun 2024

Composite wrapping of a 12-inch gas equalizer line for Dolphin Energy

Engineering, procurement and execution of composite wrapping on a 12-inch gas equalizer line at Dolphin Energy's slug catcher, at four locations.

Composite repairOnshoreGas
Client
Dolphin Energy Limited
Agreement
820/HM-00240
Location
Process area, slug catcher
Completed
30 June 2024
Status
Accepted as mechanically complete
Follow-up
Quarterly inspection for 24 months

The scope

Engineering, procurement and execution of composite wrapping for the piping spools of the 12-inch gas equalizer line (four locations) at the slug catcher.

How PEC delivered

  • Composite wrapping engineered, procured and installed by PEC at all four locations.
  • Work completed on 30 June 2024 and accepted by Dolphin Energy as mechanically complete.
  • PEC carries out quarterly inspections of the repairs for the next 24 months.
  • Mechanical completion certificate signed by Dolphin Energy in August 2024.

Signed off

The client's sign-off.

Open a document to view it in full.

Your project

Have a scope in mind?

Tell us about the asset, the location and the window you have. Our team will come back with a technical proposal and a mobilisation plan.