Case studies · Jun 2023

Ceramic composite coating during QAFCO's SDQ2 shutdown

Ceramic composite coating applied inside the sea water line, Ammonia 2 and Urea 2 during QAFCO's SDQ2 shutdown, signed off as a completed milestone.

CoatingsShutdownFertiliser
Client
Qatar Fertiliser Company (QAFCO)
Contract
706087
Location
Mesaieed, Qatar
Started
11 April 2023
Completed
12 June 2023
Scope
Sea water line · Ammonia 2 · Urea 2

The scope

Application of ceramic composite coating to the internal portions of the sea water line, Ammonia 2 and Urea 2, within QAFCO's SDQ2 shutdown window.

How PEC delivered

  • Surface preparation and ceramic composite coating applied to the internal portions of the three systems.
  • Work started on 11 April 2023; the milestone was completed on 12 June 2023.
  • QAFCO confirmed completion after its inspections, observations, testing and review of the documents PEC submitted.

Signed off

The client's sign-off.

Open a document to view it in full.