Case studies · Sep 2020

Composite wrapping of piping spools in Dolphin Energy's Unit 100

Engineering, procurement and execution of composite wrapping for piping spools in Unit 100, Stream 1, accepted as mechanically complete.

Composite repairOnshoreGas
Client
Dolphin Energy Limited
Agreement
QC-OPU-1501
Location
Unit 100, Stream 1 (FZ-14C)
Lines
100-1FA-0215 & 100-1FA-0219
Completed
1 September 2020
Follow-up
Monthly inspection for 12 months

The scope

Engineering, procurement and execution of composite wrapping for the piping spools of lines 100-1FA-0215 and 100-1FA-0219 in Unit 100, Stream 1.

How PEC delivered

  • Composite wrapping engineered, procured and installed by PEC on both lines.
  • Completed on 1 September 2020 and accepted by Dolphin Energy as mechanically complete.
  • PEC carried out monthly inspections for the following 12 months.

Signed off

The client's sign-off.