Case studies · May 2020

48-inch offshore pipeline composite repair for Qatar Petroleum

A composite repair of a 48-inch offshore pipeline for Qatar Petroleum's Marine department, delivered by PEC with 3X Engineering and completed safely during COVID-19.

Composite repairEPRS & subseaOffshore
Client
Qatar Petroleum (now QatarEnergy), Marine department
Contract
LC19105500 (tender LT19105500)
Location
Offshore, Qatar
Completed
7 May 2020
Partner
3X Engineering, Monaco
Close-out
Discharge certificate, 12 Aug 2023

The scope

Composite repair of a 48-inch offshore pipeline, awarded to PEC by tender and carried out for Qatar Petroleum's Marine department alongside its EPRS Club team.

QP Marine thanked the PEC and 3X Engineering teams for completing the job safely and to QP's requirements during COVID-19.

How PEC delivered

  • Composite repair system from 3X Engineering, installed by the PEC project team with 3X Engineering.
  • All repair works completed in early April 2020, during the COVID-19 restrictions, to QP's requirements.
  • Samples taken at every step, from priming to wrap installation, kept for testing; daily progress reports issued to QP.
  • Lessons learnt and project close-out prepared for QP's review.